EROM-26-23- Lisa DeMeo, City Engineer, requests to open the roadway to allow for a gas valve to be raised, at the intersection of Winter St and Hale St; which requires National Grid to excavate in the right of way
- 8.2.1 Order- Approve request to excavate at Winter and Hale St
- Memo from Lisa E. DeMeo, City Engineer, October 8, 2026, PDF, one page, opens in a new tab
- The order, PDF, one page, opens in a new tab
Memo from Lisa E. DeMeo, City Engineer, October 8, 2026
SUBJECT: ROAD OPENING, WINTER ST AT HALE ST, EROM-26-23
As the subject street was paved within the last 5 years, Council approval is required to open the roadway to allow for a gas valve to be raised, at the intersection of Winter St and Hale St; which requires National Grid to excavate in the right of way. I am supportive of this request, and The Engineering Office will require proper repaving from curb to curb and the limits of which will be established by city staff in the field.
Please contact me if you have any questions.
The order
That the City Council approve the request to excavate within the Winter Street right of way at the following location to raise the valve in the street at: intersection of Winter Street & Hale Street
The roadway has been paved in the last 5 years and in accordance with Chapter 222, Section 11, Restrictions on future paving of the Municipal Ordinances, Council approval is necessary.