Mayor Barrett submits a loan order appropriating $26,190,000.000 for the engineering and construction of improvements to the South Mill Street Pumping Station and Force Main
- 5.2.1 Order- That Twenty-Six Million One Hundred and Ninety Thousand Dollars
($26,190,000) is appropriated for the purpose of financing the costs of engineering and
construction of improvements to the South Mill Street Pumping Station and Force Main, including
the payment of all costs incidental or related thereto, and including without limitation all
costs thereof as defined in Section 1 of Chapter 29C of the General Laws, as most recently
amended (“Chapter 29C”)
File 10 Days
- Letter from Mayor Melinda E. Barrett, August 21, 2026, PDF, one page, opens in a new tab
- Letter from Robert E. Ward, Director of Public Works – Water/Wastewater, August 20, 2026, PDF, two pages, opens in a new tab
- Loan Order – South Mill Street Pumping Station and Force Main Improvements, PDF, one page, opens in a new tab
- Emergency PS & FM Projects, AACE Class 3 Estimate, 8/18/2026, PDF, one page, opens in a new tab